Middle Avenue Caltrain Crossing

  • Project typeTraffic and transportation
Photo simulation of the project layout

This project will construct a pedestrian and bicycle undercrossing of the Caltrain railroad near Middle Avenue, connecting Alma Street near Burgess Park to El Camino Real at the open space plaza that is part of Stanford's Middle Plaza at 500 El Camino Real project. The crossing will improve connectivity for neighborhoods on both sides of the Caltrain tracks to city amenities, schools, public transit and downtown Menlo Park.

The project is partially funded by a grant from the San Mateo County Transportation Authority's Bicycle and Pedestrian Program.

Current status

The City Council approved an updated conceptual design of the undercrossing in August 2023. Project renderings(PDF, 12MB) are available and provide several images that show what the project will look like from several viewpoints. Staff are working with Caltrain on the development of the design for the undercrossing.

A City Council study session on the next steps for the project is scheduled for Jan. 27, 2026.

Project history

The project kicked off in May 2017 and was identified as a priority project for the City Council at the April 20, 2021 City Council meeting. Direction on next steps for the project is scheduled for Jan. 27, 2026.

Date
Topic
Location
 Jan. 27, 2026 City Council meeting, provide direction on the City’s Middle Avenue Pedestrian and Bicycle Rail Crossing project City Council Chambers
 May 7, 2024 City Council meeting, authorizing the city manager to execute a memorandum of understanding with Caltrain to develop design and environmental clearance
documents
City Council Chambers
Aug. 29, 2023 City Council meeting, approving the update to the preferred concept for the Middle Avenue Caltrain crossing design City Council Chambers
July 11, 2023 City Council meeting, providing feedback on an update to the preferred concept for the Middle Avenue Caltrain crossing design

 

City Council Chambers

 

April 25, 2023

City Council meeting, adopting a resolution certifying compliance with State housing laws to be eligible for One Bay Area Grant funding for the Middle Avenue Caltrain crossing project.

City Council Chambers
April 4, 2023

City Council meeting, authorizing the city manager to execute a service agreement with Caltrain to advance the Middle Avenue Caltrain crossing project.

Belle Haven Branch Library
Jan 11, 2022 

City Council meeting, approving Purchase and Sale Agreement for a portion of 700-800 El Camino Real.

City Council online meeting
Jan 28, 2020

City Council meeting, certify environmental document and approve plans

City Council Chambers
Aug 27, 2019

City Council meeting, preferred concept selection

City Council Chambers
Jul 16, 2019

Rail Subcommittee meeting

City Hall - Downtown Conference Room
Jul 10, 2019

Complete Streets Commission meeting

City Council Chambers
Jun 4, 2019

City Council Meeting, project status update

City Council Chambers
May 13, 2019

Community meeting #2

Arrillaga Family Recreation Center
Apr 22, 2019

Rail Subcommittee meeting

City Hall Downtown Conference Room
Apr 9, 2019

City Council meeting - project status update (Informational Item)

City Council Chambers
May 4, 2017

Community Meeting #1

Menlo Church Social Hall

 